top of page


21. Importing Contract Deliverables
Importing Contract Deliverables UniPhi allows for Contract Deliverables to be imported directly into the contract page via an Excel...
Nov 8, 20231 min read


22. Contract Views
UniPhi has different views which (except for All) provide a subset of the data entered. This is due to the large amounts of data that can...
Nov 7, 20231 min read


23. Disbursements, Claim Adjustments and Retention
Disbursements Disbursements are designed to capture project related costs, which are not part of the agreed contract value. Disbursements...
Nov 6, 20232 min read


24. Contract Registers
The Details view is accessed from the Contract sub navigation options in the Contracts module. When you are editing a Contract, these...
Nov 5, 20231 min read


25. Variation Management
Best practice variation management within UniPhi involves not only the contract management components of maintaining a variation register...
Nov 4, 20232 min read


26. Add Variation to Contract
Navigate to the UniPhi Contracts module, filter for the project you are working within and drill into the contract which the variation...
Nov 3, 20232 min read


27. Variation Request and Variation Order
To advise the project team about the variation or to seek approval of it, a Variation document is generated to advise the relevant...
Nov 2, 20232 min read


28. Progress Recommendations
Progress Recommendations are the first step in assessing the contractor’s claim for payment. Create a Progress Payment Recommendation...
Nov 1, 20232 min read


29. Certifying Progress Claims
To generate a Progress Claim Certificate, the claim details are entered against each contract and its deliverables and variations. Then a...
Oct 31, 20233 min read


30. Project Cost Reports
In UniPhi Reports > Reporting -> Project Sub Nav, there are two cost reports, Project Cost Report and Project Cost Report Detail: The...
Oct 30, 20232 min read