Setting Up Estimate to Complete (ETC) and EAC
- apavel6
- Oct 31
- 1 min read
UniPhi enables powerful financial forecasting by combining your actual costs with your future resource plans.
The Calculations
Actuals (ACWP): Derived from the timesheets and expenses already entered into the system (as covered in Sections 2 & 3).
Estimate to Complete (ETC): Derived from the Forecast Resource Plan. UniPhi calculates this by taking the remaining forecast hours for every resource and multiplying them by their future charge/cost rates.
Estimate at Completion (EAC): The system automatically calculates this as Actuals + ETC .
Prerequisites
To generate these reports, you must have:
Actual timesheet and expense data.
A Forecast Resource Plan (covered in the next article).
Rates configured for your resources.




Comments