Understanding Earned Value (EV) Reporting

Oct 28, 2025
1 min read

UniPhi automatically calculates Earned Value (EV) metrics at all levels of the WBS, provided you have a Baseline Resource Plan and Progress data.


These metrics can be displayed in our PowerBi Embedded Dashboards.

Key Metrics Explained


  • BCWS (Budgeted Cost of Work Scheduled): This is the value of the work you planned to do by today. It is derived entirely from your Baseline Resource Plan (Blue Line) .

  • ACWP (Actual Cost of Work Performed): This is what you actually spent. It is derived from Timesheets x Rates .

  • BCWP (Earned Value): This is the value of the work you actually accomplished. It is calculated as Budget x % Complete.


Performance Indices


UniPhi uses these metrics to give you "at a glance" performance scores on the dashboard:

  • SPI (Schedule Performance Index): Earned Value / Budget. If < 1, you are behind schedule.

  • CPI (Cost Performance Index): Earned Value / Actual Costs. If < 1, you are over budget.