top of page

Establishing Earned Value (EV) Reporting in UniPhi

  • Feb 6
  • 4 min read

Updated: Feb 11

This article explains the end-to-end process for setting up Earned Value (EV) reporting in UniPhi.


It is intended for Project Managers and Project Administrators who are familiar with Earned Value Management concepts, but who may be new to configuring UniPhi for EV reporting.


Overview: What UniPhi Uses to Calculate Earned Value


To calculate Earned Value at all levels of the Work Breakdown Structure (WBS), UniPhi relies on three core data streams:


  • A baselined Resource Plan (budgeted labour effort and cost)

  • Actuals, captured via: Timesheets (labour) & Costs (non-resource)

  • Milestones, capturing: Progress (% complete) & Earned Value (EV) weightings


How Earned Value Is Calculated in UniPhi


At a high level, UniPhi combines:


  • Planned Value (PV) derived from: Baselined resource plans & Baselined cost budgets (resource and non-resource)


  • Actual Cost (AC) derived from: Approved timesheets & Actual cost entries


  • Earned Value (EV) derived from: Milestone progress (% complete) & Milestone EV weightings


This data is automatically rolled up from task and milestone level, through projects, and up to program and portfolio-level reporting.


Phase 1: Foundation Data Setup


1. Set Up Your Resource Pool


All EV calculations involving labour require resources to exist in UniPhi.


What to Do


  • Navigate to: Resources Module > Resources

  • Add or import project team members


Minimum Recommended Fields


  • Employee Number or Contact ID

  • Name

  • Email

  • Organisation


Resources can represent:


  • Named individuals

  • Generic roles or classifications (for example: Project Manager, Engineer)


📎 See Knowledge Base articles:


2. Ensure Resources Have Rates


Resource rates are essential for converting planned and actual hours into cost.


Key Points


Rates can be maintained:


  • At a classification/grade level, or

  • Against individual resources


Multiple rate types may be configured if required:


  • Standard

  • Overtime

  • Charge-out


Without rates, UniPhi cannot calculate:


  • Budgeted resource cost

  • Actual cost of time booked

  • Cost-based EV metrics (CPI, CV)


📎 See Knowledge Base articles:

Phase 2: Budgeting and Baselining


3. Establish the Resource Plan Budget (Labour)


The Resource Plan represents the Planned Value (PV) for labour.


What to Do


Navigate to: Resources > Resource Planning


Enter planned effort (typically hours) against:

  • WBS elements

  • Time periods

  • Resources or classifications


Notes and Tips


Resource plans can be:


  • Entered manually, or

  • Imported using UniPhi’s copy/paste from Excel feature


UniPhi automatically applies rates to calculate budgeted labour cost.


📎 See Knowledge Base articles:


4. Snapshot the Original and Approved Resource Plan


Earned Value reporting requires a baseline.


What to Do


Use the Snapshot feature in Resource Planning to:


  • Capture an Original plan

  • Approve an Approved / Baseline plan via workflow (if configured)


These snapshots:

  • Lock the Planned Value

  • Enable comparison against actuals

  • Support change control and auditability


📎 See Knowledge Base articles:


5. Establish the Budget for Non-Resource Costs


In addition to labour, Earned Value reporting often includes non-resource costs, such as:


  • Contractors

  • Materials

  • Equipment

  • Travel

Non-resource cost budgets are captured in the Cost module and contribute to project-level Earned Value.

What to Do


Navigate to:


  • Costs > Costs, and/or

  • Revenue (where applicable)


Enter budget values against the appropriate:


  • Cost categories

  • Cost codes

  • WBS elements


Important


For EV reporting, you must establish both:


  • The whole-of-project budget, and

  • The time-phased budget


The time-phased budget is used for calculating Cost Performance Index

(CPI) and time-based EV metrics.


📎 See Knowledge Base articles:




6. Create Original and Approved Snapshots for Non-Resource Costs


As with resource plans, cost budgets must be baselined.


What to Do


Use cost snapshot and baseline functionality to:

  • Capture the Original budget

  • Approve the Baseline budget


This ensures:


  • Accurate EV comparisons

  • Reliable cost variance reporting

  • Proper change management


📎 See Knowledge Base articles:



Phase 3: Progress and Earned Value Capture


7. Create Milestones for Progress and EV Weighting


UniPhi uses Milestones to calculate Earned Value progress.


Each milestone can capture:


  • % Complete

  • Earned Value weighting


Options for Creating Milestones


  • Manual entry: Navigate to: Time > Milestones

  • Milestone templates: Apply a consistent structure across the WBS

  • Integrated schedules that can be imported from Primavera P6 & Microsoft Project


Best Practice


  • Ensure milestone EV weightings total 100% at the relevant WBS level

  • Keep milestone progress up to date to ensure accurate EV calculations


📎 See Knowledge Base articles:


Phase 4: Capturing Actuals


Although not a setup step, Earned Value reporting depends on ongoing actuals capture.


Labour Actuals


  • Captured via Timesheets

  • Drive: Actual Cost (AC) & Labour-based EV metrics


Non-Resource Cost Actuals


Actual costs for non-resource items can be captured via transactions imported from an accounting system, including:


  • Accounting integrations

  • Imports via: Configuration > Timesheets > Import Expenses (Transactional)

  • Imports in the Costs module (aggregated actuals per project and cost code)

  • Signed-off progress claims from UniPhi cost contracts


📎 See Knowledge Base articles:




Phase 5: Earned Value Reporting


Once all data is in place, UniPhi provides several ways to report on Earned Value.


Program-Level Earned Value


  • Navigate to: Hamburger menu > Reports > Profitability > Program Earned Value

  • Provides rolled-up EV metrics across multiple projects


Project-Level Earned Value


  • Navigate to: Hamburger menu > Reports > Profitability > Earned Value

  • Provides detailed EV metrics for an individual project


Metrics typically include:


  • Earned Value (EV)

  • Actual Cost (AC)

  • Cost and Schedule Variances

  • CPI and SPI (where configured)


Bespoke and Executive Reporting


For more complex reporting requirements, UniPhi integrates directly with Power BI


EV data can also be used to build:


  • Executive dashboards

  • Portfolio-level trend analysis

  • Custom KPIs and visuals



📎 See Knowledge Base articles:



 
 
 

Comments


Subscribe to our UniPhi newsletter

Thanks for submitting!

  • Twitter
  • Youtube
  • Linkedin

© 2024 by UniPhi

bottom of page